Wyoming Mechanic Lien Law: Complete Guide
Your Complete Guide to Mechanic Lien Rights Under Wyo. Stat. §29-2-101 et seq. — Private Works, Preliminary Notices & Public Project Bond Claims
Wyoming mechanic lien deadline table with toggles for project type and claimant type.
Wyoming Preliminary Notice & Mechanic Lien Deadlines
Select your project type and role to see the deadlines that apply to you.
Prime Contractor — In privity with the property owner
Deliver a Notice of Right to File a Lien to the property owner before receiving any payment from the owner. Before filing the Lien Statement, also serve a Notice of Intent to Lien on the owner at least 20 days before recording the lien.
Record the Lien Statement within 150 days after last furnishing of labor or materials or substantial completion of the contract.
Commence action within 180 days after filing the Lien Statement.
Preliminary Notice
Deliver a Notice of Right to File a Lien to the property owner before receiving any payment from the owner. Before filing the Lien Statement, also serve a Notice of Intent to Lien on the owner at least 20 days before recording the lien.
Mechanic Lien
Record the Lien Statement within 150 days after last furnishing of labor or materials or substantial completion of the contract.
Enforcement
Commence action within 180 days after filing the Lien Statement.
Wyoming private project deadlines
Prime Contractor
Preliminary Notice: Deliver a Notice of Right to File a Lien to the property owner before receiving any payment from the owner. Before filing the Lien Statement, also serve a Notice of Intent to Lien on the owner at least 20 days before recording the lien.
Mechanic Lien: Record the Lien Statement within 150 days after last furnishing of labor or materials or substantial completion of the contract.
Enforcement: Commence action within 180 days after filing the Lien Statement.
Subcontractors & Suppliers
Preliminary Notice: Serve a Notice of Right to File a Lien on the property owner within 30 days after first furnishing labor or materials. Before filing the Lien Statement, also serve a Notice of Intent to Lien on the owner at least 20 days before recording the lien.
Mechanic Lien: Record the Lien Statement within 120 days after last furnishing of labor or materials.
Enforcement: Commence action within 180 days after filing the Lien Statement.
Remote Claimants
Preliminary Notice: Serve a Notice of Right to File a Lien on the property owner within 30 days after first furnishing labor or materials. Before filing the Lien Statement, also serve a Notice of Intent to Lien on the owner at least 20 days before recording the lien.
Mechanic Lien: Record the Lien Statement within 120 days after last furnishing of labor or materials.
Enforcement: Commence action within 180 days after filing the Lien Statement.
Wyoming public works deadlines
Prime Contractor
Preliminary Notice: Not applicable. The prime contractor is the principal on the payment bond and pursues payment through contract remedies, not a bond claim.
Bond Claim: Not applicable. Mechanic liens cannot attach to public property in Wyoming. Prime contractors pursue payment through contract remedies.
Lawsuit to Enforce Bond Claim: Not applicable. Prime contractors pursue contract remedies against the public owner, subject to any applicable notice-of-claim and limitations periods.
Subcontractors & Suppliers
Preliminary Notice: Serve written notice on the prime contractor within 60 days after the claimant first furnished labor or materials.
Bond Claim: Mechanic liens cannot attach to public property in Wyoming. Payment rights run through the payment bond.
Lawsuit to Enforce Bond Claim: Commence suit on the payment bond within 1 year after first publication of the notice of final payment on state projects administered by the Department of Administration and Information. On other public projects, the suit deadline is governed by the bond itself.
Remote Claimants
Preliminary Notice: Serve written notice on the prime contractor within 60 days after the claimant first furnished labor or materials.
Bond Claim: Mechanic liens cannot attach to public property in Wyoming. Payment rights run through the payment bond.
Lawsuit to Enforce Bond Claim: Commence suit on the payment bond within 1 year after first publication of the notice of final payment on state projects administered by the Department of Administration and Information. On other public projects, the suit deadline is governed by the bond itself.
Wyoming Mechanic Lien Law Overview
Last updated June 2026 · Reviewed by Thomas Emalfarb, Esq.
Wyoming construction mechanic lien rights are governed by Wyo. Stat. §29-2-101 et seq. This statutory framework provides mechanic's lien rights to contractors, subcontractors, and material suppliers who furnish labor or materials for the improvement of real property in the State of Wyoming. The statute establishes the procedures for perfecting a mechanic lien, including specific notice obligations and filing deadlines.
Wyoming does not require general contractors to serve a preliminary notice before filing a mechanic lien. However, subcontractors and suppliers on commercial projects must provide written notice to the property owner within 30 days of first furnishing labor or materials. This notice requirement helps ensure that property owners are aware of all parties furnishing labor or materials to the project.
All claimants must perfect their mechanic lien by filing a mechanic lien statement within 150 days of the date of last furnishing labor or materials. Enforcement suits must be commenced within 180 days of the date the mechanic lien was filed. Wyoming's relatively generous filing window provides claimants with meaningful time to resolve payment disputes before resorting to mechanic lien filings.
For public works projects, Wyo. Stat. §16-6-112 et seq. governs the payment bond and Wyo. Stat. §16-6-121 governs the bond-protection notice. Subcontractors and suppliers not in privity with the general contractor must give written notice to the general contractor within 60 days of first furnishing. Suit on the bond must be commenced within 1 year after first publication of the notice of final payment on state Department of Administration and Information projects; on other public projects, the language of the bond controls. National Lien & Bond provides attorney-network compliance and recovery services to help Wyoming construction professionals protect their payment rights.
Topics on This Page
Wyoming Mechanic Lien Law: Key Topics
Navigate the critical compliance areas for Wyoming construction mechanic lien law.
Notice Requirements
No preliminary notice for general contractors; subcontractors/suppliers must notify owner within 30 days of first furnishing on commercial projects
Mechanic Lien Deadlines
Mechanic Lien statement within 150 days of last furnishing for all claimants under Wyo. Stat. §29-2-101 et seq.
Mechanic Lien Enforcement Deadlines
Suit within 180 days of mechanic lien filing; public works bond suit within 1 year of the notice of final payment publication on state projects
Frequently Asked Questions
What statute governs mechanic liens in Wyoming?
Mechanic's liens in Wyoming are governed by Wyo. Stat. §29-2-101 et seq. Public works bond claims are governed by Wyo. Stat. §16-6-112 et seq.
Is a preliminary notice required to file a mechanic lien in Wyoming?
General contractors do not need a preliminary notice. Subcontractors and suppliers on commercial projects must provide written notice to the owner within 30 days of first furnishing.
What is the deadline to file a mechanic lien in Wyoming?
All claimants must file a mechanic lien statement within 150 days of the date of last furnishing labor or materials under Wyo. Stat. §29-2-101 et seq.
How does Wyoming mechanic lien law differ from other states?
Wyoming provides a generous 150-day filing window measured from last furnishing and a 180-day enforcement period. Subcontractors on commercial projects must notify the owner within 30 days, but general contractors need no preliminary notice.
What are the notice requirements for Wyoming public works bond claims?
Subcontractors and suppliers not in privity with the general contractor must give written notice to the general contractor within 60 days of first furnishing. Suit on the bond must be commenced within 1 year after first publication of the notice of final payment on state Department of Administration and Information projects; on other public projects, the bond's language controls.
What is the deadline to file suit to enforce a Wyoming construction mechanic lien?
Suit must be commenced within 180 days of the date the mechanic lien was filed. For public works bond claims, suit must be commenced within 1 year after first publication of the notice of final payment on state Department of Administration and Information projects; on other public projects, the bond's language controls.
