HomeIdaho
ID Construction Law

Idaho Mechanic Lien Law: Complete Guide

Your Complete Guide to Mechanic Lien Rights Under Idaho Statutes §45-501 to §45-517 — Private Works, Payment Bonds & Public Projects

Idaho mechanic lien deadline table with toggles for project type and claimant type.

Idaho Preliminary Notice & Mechanic Lien Deadlines

Select your project type and role to see the deadlines that apply to you.

Project Type
Select Your Tier

Prime Contractor — In privity with the property owner

Preliminary Notice

Not required on commercial projects. No pre-work preliminary notice is required for any claimant.

On residential (owner-occupied) projects, the general contractor must deliver a Disclosure Statement / Notice of Right to Lien to the homeowner at contract signing; failure to deliver can affect lien rights.

Mechanic Lien

90 days

Record the Claim of Lien with the county recorder within 90 days after completion of the labor or services, or the furnishing of materials.

Enforcement

6 months

Commence an action to foreclose the Claim of Lien within 6 months after it is recorded.

Idaho Mechanic Lien Law Overview

Idaho construction mechanic lien rights are governed by Idaho General Statutes §45-501 to §45-517 et seq. This statutory framework protects the payment rights of general contractors, subcontractors, materialmen, and suppliers who furnish labor, services, or materials for the improvement of real property in the State of Idaho.

Idaho mechanic lien law provides a streamlined process for securing payment rights. No preliminary notice is required for any claimant type on private works projects, simplifying the initial compliance burden compared to many other states. However, strict adherence to mechanic lien filing and enforcement deadlines is essential. Contractors must comply with residential disclosure requirements under Idaho Statutes §45-525 (effective July 1, 2002), and all claimants must provide notice to the property owner by certified mail within 24 hours of recording a mechanic lien.

Idaho also provides separate payment bond claim procedures for public works projects under Idaho General Statutes §54-1925 to §54-1930, which require a minimum bond of 50% of the contract amount. Where the bond exceeds 50%, retainage on public works cannot exceed 5%. On private works, retainage cannot exceed 5%, and final release of retainage may be conditioned upon delivery of mechanic lien waivers from all potential claimants.

National Lien & Bond provides authoritative guidance on every aspect of Idaho construction mechanic lien compliance, from Claim of Mechanic Lien filing through public works bond claims and mechanic lien enforcement proceedings.

Idaho mechanic lien law
Idaho Claim of Mechanic Lien deadline
How to file a mechanic lien in Idaho
Idaho mechanic lien enforcement deadline
Idaho payment bond claim
Idaho §45-507

Frequently Asked Questions

What statute governs mechanic liens in Idaho?

Mechanic liens on private construction projects in Idaho are governed by Idaho General Statutes §45-501 to §45-517 et seq. Public works payment bond claims are governed by Idaho General Statutes §54-1925 to §54-1930, which require a minimum 50% payment bond.

Is a preliminary notice required to file a mechanic lien in Idaho?

No. Idaho law does not require any preliminary notice from any claimant type — including general contractors, subcontractors, and material suppliers — as a prerequisite to filing a Mechanic's Lien on private construction projects. However, contractors must comply with the residential disclosure requirement under §45-525.

What is the deadline to file a mechanic lien in Idaho?

All claimants must record a Claim of Mechanic Lien within 90 days after substantial completion of labor or services or the furnishing of materials. Additionally, notice must be given to the property owner by certified mail within 24 hours of recording the mechanic lien. §45-507.

How does Idaho mechanic lien law differ from other states?

Idaho's mechanic lien process is notable for several reasons: no preliminary notice is required for any claimant type, all claimants share the same 90-day filing deadline measured from substantial completion, and a mandatory 24-hour certified mail notice to the property owner is required after recording the mechanic lien. Retainage on private works is capped at 5%.

What are the notice requirements for Idaho public works bond claims?

First-tier subcontractors in direct privity with the bonded contractor do not need to serve any preliminary notice. Third-tier subcontractors and material suppliers must serve a written Notice of Claim on the bonded contractor within 90 days of last performance under §54-1927.

What is the deadline to file suit on an Idaho public works payment bond?

First-tier subcontractors must file suit not less than 90 days from last performance and not more than 1 year after final payment was due under the subcontract. Third-tier claimants must file suit not less than 90 days and not more than 1 year after last performance under §54-1927.

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.

Contact Us