HomeNebraska
NE Construction Law

Nebraska Mechanic Lien Law: Complete Guide

Your Complete Guide to Mechanic Lien Rights Under Nebraska Revised Statutes §§52-125 to 52-159 — Private Works, Payment Bonds & Public Projects

Nebraska mechanic lien deadline table with toggles for project type and claimant type.

Nebraska Preliminary Notice & Mechanic Lien Deadlines

Select your project type and role to see the deadlines that apply to you.

Project Type
Select Your Tier

Prime Contractor — In privity with the property owner

Preliminary Notice

Not Required

Mechanic Lien

120 days

Record the Construction Lien with the register of deeds within 120 days after the claimant's last substantial furnishing.

Send a copy of the recorded Construction Lien to the owner within 10 days after recording.

Enforcement

2 years
30 days

Commence an action to enforce the Construction Lien within 2 years after the date of recording.

If the owner delivers a written demand to institute proceedings, the lien lapses 30 days after receipt unless the claimant sues or files an affidavit that the contract price is not yet due.

Nebraska private project deadlines

Prime Contractor

Preliminary Notice: Not required. Prime contractors in direct contract with the owner are not subject to any preliminary notice obligation.

Mechanic Lien: Record the Construction Lien with the register of deeds within 120 days after the claimant's last substantial furnishing. Send a copy of the recorded Construction Lien to the owner within 10 days after recording.

Enforcement: Commence an action to enforce the Construction Lien within 2 years after the date of recording. If the owner delivers a written demand to institute proceedings, the lien lapses 30 days after receipt unless the claimant sues or files an affidavit that the contract price is not yet due.

Subcontractors & Suppliers

Preliminary Notice: No pre-work preliminary notice is required. On owner-occupied residential projects, best practice is to serve a written Notice of Commencement-type notice of lien liability on the owner as early as possible, because the lien of a claimant not in direct contract with a protected party is capped at the amount the owner still owes the prime at the time the owner receives the notice. Suppliers to suppliers have no lien rights.

Mechanic Lien: Record the Construction Lien with the register of deeds within 120 days after the claimant's last substantial furnishing. Send a copy of the recorded Construction Lien to the owner within 10 days after recording.

Enforcement: Commence an action to enforce the Construction Lien within 2 years after the date of recording. If the owner delivers a written demand to institute proceedings, the lien lapses 30 days after receipt unless the claimant sues or files an affidavit that the contract price is not yet due.

Remote Claimants

Preliminary Notice: No pre-work preliminary notice is required. On owner-occupied residential projects, best practice is to serve a written Notice of Commencement-type notice of lien liability on the owner as early as possible, because a remote claimant's lien against a protected party is capped at the amount the owner still owes the prime at the time the owner receives the notice. Suppliers to suppliers have no lien rights.

Mechanic Lien: Record the Construction Lien with the register of deeds within 120 days after the claimant's last substantial furnishing. Send a copy of the recorded Construction Lien to the owner within 10 days after recording.

Enforcement: Commence an action to enforce the Construction Lien within 2 years after the date of recording. If the owner delivers a written demand to institute proceedings, the lien lapses 30 days after receipt unless the claimant sues or files an affidavit that the contract price is not yet due.

Nebraska public works deadlines

Prime Contractor

Preliminary Notice: Not applicable. The prime contractor is the principal on the payment bond and pursues payment through contract remedies, not a bond claim.

Bond Claim: Not applicable. Mechanic liens cannot attach to public property in Nebraska. Prime contractors pursue payment through contract remedies.

Lawsuit to Enforce Bond Claim: Contract remedies against the public owner, subject to any applicable notice-of-claim and limitations periods.

Subcontractors & Suppliers

Preliminary Notice: Not required for claimants in direct contract with the prime contractor furnishing the payment bond.

Bond Claim: File a sworn statement of claim with the officer or board awarding the public contract within 4 months after the claimant's last furnishing. Mechanic liens cannot attach to public property in Nebraska; payment rights run through the public works payment bond.

Lawsuit to Enforce Bond Claim: Commence suit on the bond within 1 year after the date of final settlement of the principal contract.

Remote Claimants

Preliminary Notice: No pre-work preliminary notice is required. Remote claimants preserve rights by timely filing the sworn statement of claim described under Bond Claim.

Bond Claim: File a sworn statement of claim with the officer or board awarding the public contract within 4 months after the claimant's last furnishing. Mechanic liens cannot attach to public property in Nebraska; payment rights run through the public works payment bond.

Lawsuit to Enforce Bond Claim: Commence suit on the bond within 1 year after the date of final settlement of the principal contract.

Nebraska Mechanic Lien Law Overview

Last updated April 2026 · Reviewed by Thomas Emalfarb, Esq.

Nebraska construction mechanic lien rights are governed by the Nebraska Revised Statutes §§52-125 to 52-159 for private works and §§52-118 to 52-118.02 for public works. This statutory framework, modeled after Article 5 of the Uniform Simplification of Land Transfers Act, protects the payment rights of contractors, subcontractors, materialmen, architects, engineers, and other persons who furnish services or materials for the improvement of real property in Nebraska.

Under Nebraska law, a construction mechanic lien may be claimed by any person who furnishes services or materials pursuant to a real estate improvement contract — defined as an agreement to perform services, including labor, or to furnish materials for the purpose of producing a change in the physical condition of land or a structure. Materials covered include those incorporated into the structure, used for construction or equipment operation, and tools or machinery used on the project. Suppliers to suppliers, however, have no right to file a construction mechanic lien.

Nebraska's construction mechanic lien system provides a structured framework of preliminary notices, mechanic lien recording deadlines, and enforcement timelines. The state also permits contracting owners to file a Notice of Commencement (§52-145), which affects mechanic lien priority and attachment dates. For public works projects, Nebraska requires a 100% payment bond and provides separate bond claim procedures under §§52-118 to 52-118.02.

National Lien & Bond provides authoritative guidance on every aspect of Nebraska construction mechanic lien compliance, from notice of mechanic lien liability requirements through mechanic lien recording, public payment bond claims, and mechanic lien enforcement proceedings.

Frequently Asked Questions

What types of construction mechanic liens are available in Nebraska?

Nebraska provides construction mechanic lien rights for private works under Revised Statutes §§52-125 to 52-159. Any person who furnishes services or materials pursuant to a real estate improvement contract — including contractors, subcontractors, materialmen, architects, and engineers — may file a construction mechanic lien. However, suppliers to suppliers have no right to file. For public works projects, mechanic liens are not available; instead, claimants must pursue payment through a suit on the 100% payment bond under §§52-118 to 52-118.02.

What is the deadline to file a construction mechanic lien in Nebraska?

A construction mechanic lien must be recorded not later than 120 days after the date the last substantial services or materials were furnished (§52-137). Insignificant punch list work or delivery of an insignificant portion of materials may not extend this deadline. After recording, the claimant must send a copy of the recorded mechanic lien to the "protected party contracting owner" within 10 days (§52-135).

How long is a construction mechanic lien enforceable in Nebraska?

A construction mechanic lien is enforceable for 2 years from the date of recording. However, if the contracting owner delivers a demand to institute judicial proceedings, the mechanic lien will lapse 30 days after receipt unless the claimant either commences suit or files an affidavit that the contract price is not yet due. Filing suit extends the mechanic lien until the judicial proceedings terminate.

What is a Notice of Commencement and how does it affect mechanic lien priority in Nebraska?

A Notice of Commencement may be filed by the contracting owner under §52-145. Mechanic Liens filed while the Notice of Commencement is effective attach at the time of filing of the Notice of Commencement. Mechanic Liens filed after termination of the Notice of Commencement attach the day after termination. If no Notice of Commencement is recorded, mechanic liens attach as of the date of visible commencement of the improvement.

What are the public works payment bond claim requirements in Nebraska?

On public works projects, a claimant who has not been paid within 90 days after last furnishing labor or material may file suit against the payment bond (§52-118.01). The suit must be filed no later than 1 year after the final settlement of the principal contract (§52-118.02). Sub-subcontractors without a direct contractual relationship with the general contractor must give written notice within 4 months from their last furnishing date.

Does Nebraska require a preliminary notice before filing a construction mechanic lien?

Nebraska does not require a formal preliminary notice as a prerequisite to filing a construction mechanic lien. However, a claimant may give a written notice of mechanic lien liability to the Contracting Owner at any time after entering into the contract (§52-135). This notice is strongly recommended because a subcontractor's mechanic lien against a "protected party" is limited to the lesser of the amount owed under the subcontract or the amount unpaid under the prime contract at the time the protected party receives notice.

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.

Contact Us