Prime Contractor — Contractor's Preliminary Notice (§779.02(2))
Prime contractors must serve a Contractor's Preliminary Notice on the property owner informing the owner of potential claims of subcontractors. This notice must be included in all written contracts or served within 10 days after first labor or materials are furnished if there is no written contract. The form and language of the notice are specified generally in the statute. §779.02(2).
This notice advises the owner that subcontractors and suppliers may have mechanic lien rights on the property and is designed to ensure owners are aware of their potential exposure before or shortly after construction begins.
Subcontractors & Suppliers — Non-Contractor's Preliminary Notice (§779.02(1))
For residential projects of 4 or fewer family units only, subcontractors and suppliers must serve a Non-Contractor's Preliminary Notice. Two copies must be served on the owner of potential claims within 60 days of first performance or delivery by the subcontractor or supplier. The form and language are specified generally in the statute. §779.02(1), §779.02(2)(b).
There is no limit on the number of tiers of subcontractors that may claim mechanic lien rights, with certain statutory exceptions. However, if the prime contractor furnishes a payment bond meeting the requirements of §779.035, subcontractor and material supplier mechanic lien rights are extinguished and claims must be made against the bond.
Notice of Intent to File a Mechanic Lien Claim (§779.06(2))
All claimants — both prime contractors and subcontractors — must serve a Notice of Intent to File a Mechanic Lien Claim on the property owner at least 30 days before the timely filing of the mechanic lien claim, after substantial completion of the specific contractor's work. §779.06(2).
This mandatory pre-filing notice gives the owner a 30-day window to resolve the dispute before the mechanic lien is actually filed. Failure to serve this notice may invalidate the mechanic lien claim.
Payment Bond Claims — 60-Day Written Notice (§779.035(2))
When a prime contractor furnishes a payment bond, subcontractors and suppliers must notify the prime contractor in writing within 60 days of first performance to preserve their bond claim rights. Exceptions apply when: the contract does not exceed $5,000; the subcontractor or supplier is listed in the written contract or an appended document; or the claim is made by an employee.
The same 60-day notice applies on public works projects under §779.14(2). The subcontractor must notify the public body and prime contractor in writing within 60 days of first performance, with the same exceptions as private bond claims.
Mechanic Lien on Funds — Notice of Claim (§779.036)
Where a payment bond has been issued on private works, subcontractors and suppliers may also pursue a mechanic lien on funds not yet paid to the contractor. A Notice of Claim must be served on the owner and lender prior to funds being paid to the contractor, and on the contractor or subcontractor within 7 days after service on the owner and lender. Notice must also be served concurrently on the prime contractor.
If the contractor does not dispute the claim, the claim must be paid on demand within 30 days. §779.036(1)-(3).
Equipment Lessors — No Mechanic Lien Rights
Equipment lessors do not have mechanic lien rights under Wisconsin law. Lessors cannot file a Claim of Mechanic Lien or make a bond claim for equipment rentals. This is an important distinction from many other states that provide mechanic lien rights to equipment rental companies.
Frequently Asked Questions
Is a preliminary notice required to file a mechanic lien in Wisconsin?
Yes. Prime contractors must serve a Contractor's Preliminary Notice in written contracts or within 10 days of first furnishing. Subcontractors on residential projects (4 or fewer units) must serve a Non-Contractor's Preliminary Notice within 60 days. All claimants must serve a Notice of Intent to File at least 30 days before filing the mechanic lien.
What is the Notice of Intent to File a Mechanic Lien Claim in Wisconsin?
Under §779.06(2), all claimants must serve a Notice of Intent to File a Mechanic Lien Claim on the owner at least 30 days before filing the mechanic lien, after substantial completion of the contractor's work. This mandatory notice gives the owner time to resolve the dispute before the mechanic lien is filed.
Do equipment lessors have mechanic lien rights in Wisconsin?
No. Equipment lessors do not have mechanic lien rights under Wisconsin law. They cannot file a Claim of Mechanic Lien or make bond claims for equipment rentals.
What happens if the prime contractor provides a payment bond in Wisconsin?
Under §779.035 and §779.03(2), if the prime contractor furnishes a qualifying payment bond, subcontractor and material supplier mechanic lien rights are extinguished. All claims must then be made against the bond instead of by filing a mechanic lien on the property.
What is the mechanic lien on funds remedy in Wisconsin?
Under §779.036, where a payment bond has been issued, subcontractors may serve a Notice of Claim on the owner and lender before funds are paid to the contractor. If the contractor does not dispute within 30 days, the claim must be paid. If disputed, suit must be filed within 3 months.
Related Wisconsin Resources
Explore other critical compliance areas for Wisconsin construction mechanic lien law.
Mechanic Lien Deadlines
6-month Claim of Mechanic Lien filing deadline, Notice of Intent 30-day pre-filing requirement, and payment bond extinguishment rules
Mechanic Lien Enforcement Deadlines
2-year suit deadline, payment bond claims within 1 year, mechanic lien on funds suit within 3 months, and public works enforcement
Payment Bond Claims
Private bond rights under §779.035, public works bond claims under §779.14, 60-day notice requirements, 1-year suit deadlines, and lien on funds procedures
Wisconsin Overview
Return to the main Wisconsin construction mechanic lien law page
