Private Works — 2-Year Suit Deadline (§779.06(1))
Under Wisconsin law, a mechanic lien claimant must file suit to foreclose the Claim of Mechanic Lien within 2 years after the mechanic lien is recorded with the Clerk of Circuit Court. This is one of the longest enforcement periods in the United States.
Failure to commence suit within the 2-year period will result in the expiration of the mechanic lien. Despite the generous window, claimants should not delay enforcement unnecessarily, as the property owner may seek to discharge the mechanic lien.
Private Works — Payment Bond Suit Deadline (§779.035(2))
When the prime contractor has furnished a qualifying payment bond and mechanic lien rights are extinguished, subcontractors and suppliers must file suit against the surety within 1 year after completion of the contract according to the terms of the payment bond. §779.035(2).
Claimants must have served written notice to the prime contractor within 60 days of first performance to preserve bond claim rights, unless one of the statutory exceptions applies (contract under $5,000, listed in the contract, or employee claim).
Private Works — Mechanic Lien on Funds Suit Deadline (§779.036(3))
When pursuing a mechanic lien on funds not yet paid to the contractor (where a payment bond was issued), the claimant must file suit within 3 months after the Notice of Claim is served on the owner and lender, if the contractor disputes the claim. If the contractor does not dispute the claim, it must be paid on demand within 30 days.
Public Works — Payment Bond Suit Deadline (§779.14(2))
On Wisconsin public works projects, subcontractors and suppliers must file suit within 1 year after completion of work under the prime contract, naming the prime contractor and bond sureties. §779.14(2).
The same 60-day written notice to the public body and prime contractor is required as for private payment bonds, with the same statutory exceptions. Coverage on public works generally extends to subcontractors and first-tier suppliers with direct contracts with the prime contractor or a first-tier subcontractor.
Public Works — Mechanic Lien on Funds Due Prime Contractor (§779.15)
Subcontractors and suppliers may also pursue a mechanic lien on funds due the prime contractor from the public body. A Notice of Claim must be sent to the public body while there is still a balance due to the prime contractor — there is no specific deadline, but the notice must be sent while funds remain available.
If the prime contractor disputes the claim, suit must be filed within 3 months of giving notice to the public body and prime contractor. §779.15.
Summary of Wisconsin Enforcement Deadlines
The following deadlines apply to enforcement of Wisconsin construction mechanic liens and bond claims:
- Private Works Mechanic Lien: File suit within 2 years after mechanic lien is recorded (§779.06(1))
- Private Payment Bond: File suit within 1 year after contract completion (§779.035(2))
- Private Mechanic Lien on Funds: File suit within 3 months if contractor disputes (§779.036(3))
- Public Works Bond: File suit within 1 year after completion of prime contract (§779.14(2))
- Public Works Mechanic Lien on Funds: File suit within 3 months if contractor disputes (§779.15)
Frequently Asked Questions
What is the deadline to file a mechanic lien enforcement suit in Wisconsin?
Suit must be filed within 2 years after the Claim of Mechanic Lien is recorded with the Clerk of Circuit Court under §779.06(1). This is one of the longest enforcement periods in the nation.
What is the deadline for Wisconsin payment bond claims?
For both private (§779.035(2)) and public works (§779.14(2)), suit must be filed within 1 year after completion of the contract. Subcontractors must have given 60-day written notice of first performance to preserve bond rights.
What is the mechanic lien on funds suit deadline in Wisconsin?
If the contractor disputes a mechanic lien on funds claim, suit must be filed within 3 months after the Notice of Claim is served under §779.036(3) for private works and §779.15 for public works. If not disputed, payment is due within 30 days.
Do second-tier subcontractors have public works bond rights in Wisconsin?
Coverage is generally limited to subcontractors and first-tier suppliers with direct contracts with the prime or first-tier subcontractor. Recent statutory amendments make it unclear whether second or subsequent tier suppliers have mechanic lien rights to public work funds under the Wisconsin Construction Mechanic Lien Act.
What happens if the contractor does not dispute a Wisconsin mechanic lien on funds claim?
Under §779.036(1)-(3), if the contractor does not dispute the claim, it must be paid on demand within 30 days of the Notice of Claim being served on the owner and lender.
Related Wisconsin Resources
Explore other critical compliance areas for Wisconsin construction mechanic lien law.
Notice Requirements
Contractor's and Non-Contractor's Preliminary Notice, Notice of Intent to File a Mechanic Lien Claim, payment bond notice, and mechanic lien on funds notice procedures
Mechanic Lien Deadlines
6-month Claim of Mechanic Lien filing deadline, Notice of Intent 30-day pre-filing requirement, and payment bond extinguishment rules
Payment Bond Claims
Private bond rights under §779.035, public works bond claims under §779.14, 60-day notice requirements, 1-year suit deadlines, and lien on funds procedures
Wisconsin Overview
Return to the main Wisconsin construction mechanic lien law page
