Private Works — 180-Day Suit Deadline
Under Utah law, a mechanic lien claimant must file suit to foreclose the Notice of Mechanic Lien within 180 days after recording the Notice of Mechanic Lien. This deadline is measured from the recording date, not from last furnishing.
The 180-day enforcement period is relatively short compared to many states. Claimants should begin preparing their enforcement action promptly after recording the mechanic lien to avoid missing this critical deadline.
Private Commercial — Payment Bond Claims (§14-2-1 et seq.)
Utah requires 100% payment bonds on all commercial projects over $50,000 under §14-2-1 et seq. Subcontractors and material suppliers may file suit on the bond not less than 90 days after last performance but no more than 1 year after last performance by the claimant.
Second-tier subcontractors and suppliers not in privity with the original contractor must have filed a Preliminary Notice to the bond principal within 20 days of first performance.
Public Works — Payment Bond Claims (§14-1-1 et seq.)
Utah public works projects also require 100% payment bonds under §14-1-1 et seq. The suit deadline is the same: not less than 90 days and not more than 1 year after last performance by the claimant.
Second-tier claimants on public works must also file a Preliminary Notice to the bond principal within 20 days of first performance. If no bond was required by the owner, claimants must give notice within 90 days of final furnishing to preserve the right to sue the owner.
Owner Liability for Failure to Require Bond
Under both §14-2-1 (private commercial) and §14-1-1 (public works), if the owner fails to require the mandatory payment bond, the owner may be held personally liable to subcontractors and suppliers for unpaid amounts. This provides an important alternative remedy when bonds are not properly procured.
Frequently Asked Questions
What is the deadline to file a mechanic lien enforcement suit in Utah?
Suit must be filed within 180 days after recording the Notice of Mechanic Lien. This is measured from the recording date and is relatively short compared to many states.
What is the deadline for Utah payment bond claims?
For both private commercial (§14-2-1) and public works (§14-1-1), suit must be filed not less than 90 days and not more than 1 year after last performance by the claimant.
What happens if the owner doesn't require a bond in Utah?
Under both §14-2-1 (private commercial over $50,000) and §14-1-1 (public works), the owner may be held personally liable to subcontractors and suppliers if the required payment bond was not procured.
Do second-tier claimants need notice for Utah bond claims?
Yes. Second-tier subcontractors and suppliers not in privity with the original contractor must file a Preliminary Notice to the bond principal within 20 days of first performance on both private commercial and public works projects.
What is the minimum bond amount on Utah commercial projects?
Utah requires a 100% payment bond on all commercial projects over $50,000 under §14-2-1 et seq. Public works projects also require 100% bonds under §14-1-1.
Related Utah Resources
Explore other critical compliance areas for Utah construction mechanic lien law.
Notice Requirements
Notice of Commencement within 15 days, Preliminary Notice within 20 days, signed invoice 15 days before mechanic lien, and second-tier bond notice
Mechanic Lien Deadlines
Notice of Mechanic Lien within 90 days of Notice of Completion or 180 days from final completion, residential restrictions, and Mechanic Lien Recovery Fund
Utah Overview
Return to the main Utah construction mechanic lien law page
