HomeIllinoisNotice Requirements
IL Notice Requirements

Illinois Notice Requirements

Tiered Statutory Notice Obligations Under the Illinois Mechanics Lien Act (770 ILCS 60)

General Contractor — Sworn Statement Requirement (770 ILCS 60/5)

Before receiving payment, general contractors must provide the property owner with a Sworn Statement listing "all parties furnishing materials and labor and the amounts due or to become due to each." This is required under 770 ILCS 60/5.

For owner-occupied residences, the general contractor must also have a written contract and must give (and receive a signed receipt for) a consumer rights pamphlet to the homeowner. Failure to comply with these requirements can jeopardize the contractor's mechanic lien rights on residential projects.

Subcontractor 90-Day Notice — To Owner & Lender (770 ILCS 60/24, 60/28)

Subcontractors and material suppliers must serve a 90-Day Notice on both the property Owner and the Lender. This notice may be served any time after the contract is entered into, but must be served within 90 days after completion of work or final delivery of materials. This is required under 770 ILCS 60/24 and 60/28.

After serving the 90-Day Notice, the subcontractor may record a Claim for Lien with the county recorder, but cannot commence a suit to enforce the lien until 10 days after service of the notice. 770 ILCS 60/28. Failure to serve the notice within the 90-day window bars the subcontractor from recording a mechanic lien.

Serving Early — Why Timing Affects the Value of the Lien

The 90-Day Notice can be served any time after the subcontract is entered into. The statute preserves lien rights as long as the notice reaches the owner and lender within 90 days after last furnishing, but the dollar value of the resulting mechanic lien depends on when within that window the notice is served.

Illinois is an unpaid-balance state: a subcontractor's mechanic lien attaches only to the amount the owner still owes the general contractor when the lien is perfected. If the 90-Day Notice is held until the end of the statutory window, the owner may have already released most or all of the contract balance to the GC, leaving a smaller fund — or none — for the subcontractor's lien to reach.

Serving the 90-Day Notice shortly after signing the subcontract is the strongest protection. Statutory compliance is satisfied the same way, but early service secures the claim against the largest possible unpaid contract balance and puts the owner on notice before further payments flow downstream.

Sworn Statement Exception to 90-Day Notice

While strict compliance is the rule, 770 ILCS 60/24 and 770 ILCS 60/21 provide an important exception. If the General Contractor provided a Sworn Statement to the owner that correctly identifies the subcontractor and the amount due, that statement can serve as sufficient notice to the owner to the extent of the amount shown.

This exception can preserve mechanic lien rights for subcontractors who missed the 90-day deadline, but only to the extent of the amount listed on the General Contractor's sworn statement.

60-Day Notice — Owner-Occupied Single-Family Residences (770 ILCS 60/5, 60/21)

For projects involving owner-occupied single-family residences, subcontractors must provide a written "Notice to Owner" within 60 days of their first date of furnishing material or labor. This requirement is governed by 770 ILCS 60/5 and 60/21.

This 60-day notice is measured from the first date of furnishing — not the last — making it particularly easy to miss. Subcontractors working on residential projects should serve this notice as early as possible to avoid forfeiture.

10-Day Notice — Before Recording Mechanic Lien on Owner-Occupied Residence (770 ILCS 60/7)

For owner-occupied single-family residences, both general contractors and subcontractors must give notice to the owner within 10 days of recording the mechanic lien. This requirement applies under 770 ILCS 60/7.

The purpose is to provide homeowners with direct awareness that a mechanic lien has been placed on their property and an opportunity to resolve payment disputes.

Public Works — Notice of Claim on Payment Bond (30 ILCS 550/2)

On public construction projects in Illinois exceeding $5,000, the general contractor is required to provide a payment bond under the Illinois Public Construction Bond Act (30 ILCS 550). No preliminary notice is required for bond claims.

Subcontractors and material suppliers must serve a Notice of Claim on Bond to the Public Authority within 180 days after the "last item of work" or furnishing of the "last item of materials." A copy of the notice must also be sent to the contractor within 10 days thereafter. 30 ILCS 550/2.

Public Works — Notice for Mechanic Lien on Unexpended Public Funds (770 ILCS 60/23)

For mechanic liens on unexpended public funds, subcontractors and material suppliers must serve notice to the clerk, secretary, or director of the Public Authority and to the contractor prior to payment of funds. Mechanic Lien rights are limited to funds owed to the claimant's immediate contractor at the time of the claim. 770 ILCS 60/23(b) and (c).

If the contractor serves a demand, the claimant must respond within 30 days thereafter. 770 ILCS 60/23(b) and (c).

Service Methods

Section 24(a) allows the following methods of serving statutory mechanic lien notices, and the notice is considered served at the time it is placed with the delivery service or in the mail:

  • Registered or certified mail, return receipt requested
  • A nationally recognized delivery company with tracking service
  • Personal service

Why Strict Compliance Matters for Notices

Illinois courts do not recognize "close enough" when it comes to notice requirements. Improperly serving notices to owners or lenders, or failing to adhere to the strict timelines, can result in the complete forfeiture of mechanic lien rights. Subcontractors and suppliers should implement compliance tracking systems to ensure all notices are served within the statutory windows.

Frequently Asked Questions

What is the Illinois 90-day notice for subcontractors?

Under 770 ILCS 60/24, subcontractors must serve a 90-Day Notice on both the Owner and the Lender within 90 days after completion of work or final delivery. The claim for lien may be recorded after service. A suit to enforce the lien cannot be commenced, however, until 10 days after service of the notice (770 ILCS 60/28).

When should I serve the Illinois 90-Day Notice?

The notice can be served any time after the subcontract is signed, and must be served within 90 days after last furnishing. Because Illinois is an unpaid-balance state, earlier is stronger: the subcontractor's lien is capped at what the owner still owes the GC when the lien attaches, so serving shortly after contract signing secures the claim against the largest possible unpaid contract balance. Waiting until the end of the 90 days risks the owner having already paid the GC down to a smaller fund — or nothing at all.

What happens if I miss the 90-day notice deadline?

Not necessarily a forfeiture. If the General Contractor provided a sworn statement to the owner that correctly identifies you and the amount due, that statement can serve as sufficient notice under 770 ILCS 60/21 and 60/24, to the extent of the amount shown.

What is the Illinois 60-day residential notice?

For owner-occupied single-family residences, subcontractors must provide a written Notice to Owner within 60 days of their first date of furnishing material or labor under 770 ILCS 60/5 and 60/21. Note this is measured from the first date of furnishing, not the last.

What is the contractor's Sworn Statement requirement?

Under 770 ILCS 60/5, general contractors must provide the owner with a Sworn Statement listing all parties furnishing materials and labor and the amounts due or to become due to each, before receiving payment.

What is the bond notice deadline on Illinois public projects?

Under 30 ILCS 550/2, you must serve a Notice of Claim on Bond to the Public Authority within 180 days of your last work or material delivery, and send a copy to the contractor within 10 days thereafter.

Do I need a preliminary notice for public works bond claims?

No preliminary notice is required for payment bond claims on Illinois public projects. However, you must serve the Notice of Claim on Bond within 180 days of your last work date under 30 ILCS 550/2.

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.

Contact Us