HomeFloridaNotice Requirements
FL Notice Requirements

Florida Notice Requirements

Preliminary Notice Obligations for Private Works, Private Bonds & Public Projects Under Florida Statutes

Private Works — Notice to Owner (§713.06)

Under Florida law, a lienor who is not in direct privity with the owner must serve a written Notice to Owner before commencing, or not later than 45 days after commencing, to furnish services or materials. For specially manufactured materials, the notice must be served at the start of manufacture. In any event, the notice must be served before the owner's disbursement of final payment. §713.01(2)(a)3.

Failure to give timely notice is a complete defense to enforcement of the mechanic lien. §713.06(2)(a). The statutory form of notice should be used. §713.06(2)(c). Notice to Owner is effective upon receipt, not mailing. §713.18.

Who Must Serve and Receive the Notice to Owner

The following parties must serve a Notice to Owner, and the notice must also be served on the appropriate recipients:

  • Subcontractors not in direct privity with the owner must serve the owner
  • Sub-subcontractors or materialmen to subcontractors must also serve a copy of the notice on the contractor
  • Materialmen to sub-subcontractors must serve a copy on both the contractor and the subcontractor (if name and address are known)

Service Methods — All Florida Notices

All Florida mechanic lien and bond notices must be given by one of the following methods:

  • Certified mail, return receipt requested
  • Hand delivery (actual delivery)
  • Posting is permissible only if hand delivery and certified/registered mail cannot be accomplished — and you must have attempted those methods first. §713.18
  • If sent registered or certified within 40 days of first furnishing, and a certified mail log is kept with USPS stamp confirming date of mailing, notice is effective as of date of mailing. §713.18(1)(b)1

Sworn Statement of Account on Demand (§713.16)

Upon written demand, a lienor must provide within 30 days a sworn statement of account containing information on the nature and quantity of services and materials, labor amount paid, and amount due. If the lienor fails to provide this statement within 30 days of the demand, the lienor is deprived of its mechanic lien. §713.16(2). The statutory form must be used. §713.16(3).

Impact of the Notice of Commencement

The Notice of Commencement is a document recorded by the property owner before construction begins. It identifies the owner, contractor, lender, and legal description of the property. Subcontractors and suppliers rely on the Notice of Commencement to identify the parties who must receive the Notice to Owner.

If no Notice of Commencement has been recorded, mechanic lien claimants may still preserve their rights, but the procedural requirements for service may differ.

Private Payment Bond — Notice to Contractor (§713.23)

On private projects where the owner requires a payment bond, a lienor not in privity with the contractor must serve the contractor with a written Notice to Contractor within 45 days after beginning to furnish labor, materials, or supplies (or at start of manufacture for specially manufactured materials). §713.23(1)(c).

If no Notice of Commencement is recorded, or the Notice of Commencement does not refer to the bond, and the lienor is not otherwise notified of the bond's existence, the lienor has 45 days from the date they are notified of the bond to serve the notice. The statutory form should be used.

Private Payment Bond — Notice of Nonpayment (§713.23(1)(d))

As a condition precedent to recovery under a private payment bond, a lienor must serve written Notice of Nonpayment on the contractor and the surety no later than 90 days after the lienor's final furnishing of labor, services, or materials. §713.23(1)(d).

Retainage that does not exceed 10% of the labor, services, or materials furnished is not considered a nonpayment requiring service of this notice. The statutory form should be used. The mechanic lien should be recorded along with the Notice of Nonpayment.

If the bond is a conditional bond (§713.245), the mechanic lien MUST be filed to perfect bond claim rights.

Public Works — Subcontractors in Privity with General Contractor (§255.05)

Under Florida's "Little Miller Act" (§255.05), subcontractors or material suppliers who are in direct privity with the general contractor are not required to serve any preliminary notice or notice of nonpayment on public projects. No mechanic lien can be filed against public property.

Public Works — Claimants NOT in Privity with General Contractor (§255.05)

Claimants not in privity with the prime contractor must serve two notices on public projects:

  • Notice of Intent to Look to the Bond: Within 45 days after beginning to furnish labor, materials, or supplies (except specially manufactured materials), the claimant must furnish the prime contractor with written notice of intent to look to the bond for protection. §255.05
  • Notice of Nonpayment (Public Property): Within 90 days after performance of the labor or complete delivery of materials and supplies (or for rental equipment, within 90 days after the equipment was last on the job site), but not before 45 days after first furnishing. The claimant must deliver written notice to the contractor and to the surety. §255.05

Public Works — Demand for Sworn Statement

On public projects, the general contractor has the right to serve a demand for sworn statement of account on any bond claimant. If the claimant fails to provide the statement within 30 days of the demand, the claimant's bond claim is lost.

Consequences of Failing to Serve Notice

The consequences of failing to serve timely and proper notices in Florida are severe. Failure to give timely Notice to Owner is a complete defense to enforcement of the mechanic lien. §713.06(2)(a). Any waiver of a right to claim a mechanic lien that is made in advance is unenforceable. §713.20(2).

Frequently Asked Questions

Who must serve a Notice to Owner in Florida?

Any lienor not in direct privity with the property owner must serve a Notice to Owner within 45 days of first furnishing labor, services, or materials. Sub-subcontractors must also serve a copy on the contractor; materialmen to sub-subcontractors must serve the contractor and subcontractor. §713.06.

What is the deadline for serving a Florida Notice to Owner?

The Notice to Owner must be served before commencing, or within 45 days after commencing to furnish services or materials. For specially manufactured materials, it must be served at the start of manufacture. In all cases, it must be served before the owner disburses final payment.

What happens if I miss the Notice to Owner deadline in Florida?

Failure to give timely notice is a complete defense to enforcement of the mechanic lien under §713.06(2)(a). You lose mechanic lien rights for work performed before the notice is eventually served.

What is the Notice of Nonpayment on a private bond?

Under §713.23(1)(d), a lienor must serve written Notice of Nonpayment on the contractor and surety within 90 days of final furnishing. Retainage of 10% or less is not considered nonpayment. The mechanic lien should be recorded along with the notice.

What notices are required on Florida public projects?

Subs in privity with the GC need no notice. Subs NOT in privity must serve a Notice of Intent to Look to the Bond within 45 days of first furnishing, and a Notice of Nonpayment within 90 days of last furnishing (but not before 45 days after first furnishing). §255.05.

Can I file a mechanic lien on a public project in Florida?

No. Florida law prohibits mechanic liens on public property. Payment rights on public projects are secured through payment bond claims under Florida's Little Miller Act, §255.05.

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.

Contact Us