Direct Contractors — 180-Day Filing Deadline
A contractor who has made a contract directly with the owner and has furnished both labor and materials must file a mechanic lien before the expiration of 180 days after completion of the project. 25 Del.C. §2711(a). No preliminary notice or other notices are required prior to filing.
This 180-day deadline applies specifically to contractors in direct privity with the property owner who have provided both labor and materials. Contractors who furnished only labor or only materials may be subject to different filing requirements and should consult the applicable statutory provisions.
Subcontractors & Suppliers — 120-Day Filing Deadline
All other persons who have performed or furnished labor or material, or both, must file a Statement of Claim within 120 days after completion of labor or last delivery of material. 25 Del.C. §2711(b). This category includes subcontractors, sub-subcontractors, material suppliers, and any other claimant not in direct privity with the owner.
The 120-day period begins to run from the completion of the claimant’s own labor or the last delivery of the claimant’s materials, not from the overall project completion date. Accurate record-keeping of the last date of furnishing is essential for calculating this deadline.
Small Claims — Labor Under $100
Any person performing labor with a value under $100 may file a Statement of Claim in the Justice of the Peace Court. The filing may be made not sooner than 20 days after the last labor performed, but must be filed within 30 days after the last performance. 25 Del.C. §2732.
This provision creates a narrow filing window for small labor claims, requiring claimants to wait at least 20 days but file no later than 30 days after the last labor is performed. Missing either boundary of this window will result in the loss of mechanic lien rights for the claim.
Definition of “Completion” for Direct Contractors
Completion of the project or structure is a critical concept in Delaware mechanic lien law because it triggers the 180-day filing deadline for direct contractors. Under 25 Del.C. §2711(a) 1-9, completion is defined as any one of the following events:
- The date of completion stated in the contract
- The date when the statute of limitation runs, as stated in the contract, for a specific phase or stage of a project, or for the entire project
- The date when the contractor receives payment of 90% of the contract price plus the amount of change orders
- The date the contractor submits a final invoice to the owner
- The date a certificate of occupancy is issued for the structure
- The date the owner accepts the structure
- The date the engineer or architect issues a certificate of completion
- The date permanent financing is completed
Definition of “Completion” for Subcontractors & Suppliers
For subcontractors and other non-direct claimants, the completion of labor or last delivery of material triggers the 120-day filing deadline. Under 25 Del.C. §2711(a) 1-9, this is defined as either:
- The date final payment, including retainage, is due to the claimant
- The date final payment is made to the contractor who has a contract with the owner to erect, alter, or repair a structure, and is to furnish labor and/or materials to perform the work
Minimum Claim Value & Filing Procedures
Delaware mechanic lien rights are available for projects with a value exceeding $25.00. Claims below this threshold do not qualify for mechanic lien protection under the statute. For claims of labor under $100, the Justice of the Peace Court has jurisdiction under the special small claims provisions of 25 Del.C. §2732.
The Statement of Claim must contain sufficient information to identify the property, the nature of the labor or materials provided, the amount claimed, and the parties involved. Claimants should ensure that all filings comply with the applicable county recording requirements and procedural rules.
Frequently Asked Questions
What is the mechanic lien filing deadline for a direct contractor in Delaware?
A contractor who has a direct contract with the owner and has furnished both labor and materials must file a mechanic lien before the expiration of 180 days after completion of the project. 25 Del.C. §2711(a). The definition of ‘completion’ includes multiple triggering events such as contract date, certificate of occupancy, or owner acceptance.
What is the mechanic lien filing deadline for subcontractors and suppliers in Delaware?
Subcontractors, material suppliers, and all other persons who have performed or furnished labor or material must file a Statement of Claim within 120 days after completion of labor or last delivery of material. 25 Del.C. §2711(b). The deadline runs from the claimant’s own last furnishing date.
How is ‘completion’ defined under Delaware mechanic lien law?
For direct contractors, completion is defined as any one of eight events under 25 Del.C. §2711(a) 1-9, including the contract completion date, receipt of 90% of the contract price, issuance of a certificate of occupancy, owner acceptance, submission of final invoice, or completion of permanent financing. The earliest applicable event triggers the deadline.
What is the filing procedure for small labor claims under $100 in Delaware?
Persons performing labor valued under $100 may file a Statement of Claim in the Justice of the Peace Court. The claim must be filed not sooner than 20 days after the last labor performed, but within 30 days after the last performance. 25 Del.C. §2732. This creates a narrow 10-day filing window.
What is the minimum claim value for a Delaware mechanic lien?
Delaware mechanic lien rights are available for projects with a value exceeding $25.00. Claims at or below $25.00 do not qualify for mechanic lien protection. For labor claims under $100, a special small claims procedure through the Justice of the Peace Court is available under 25 Del.C. §2732.
Related Delaware Resources
Explore other critical compliance areas for Delaware construction mechanic lien law.
Notice Requirements
Preliminary notice obligations and statutory notice provisions for private and public works projects under Delaware law
Mechanic Lien Enforcement Deadlines
Suit filing requirements to perfect mechanic liens, bond claim enforcement timelines, and public works litigation deadlines
Delaware Overview
Return to the main Delaware construction mechanic lien law page
