HomeColoradoMechanic Lien Enforcement Deadlines
CO Mechanic Lien Enforcement Deadlines

Colorado Mechanic Lien Enforcement Deadlines

Foreclosure, Bond Claim Suits & Enforcement Timelines Under Colorado Revised Statutes

Private Works — Suit After Performance But Within 6 Months of Completion (C.R.S. §3249)

Under Colorado law, suit to enforce a mechanics' mechanic lien may be filed at any time after performance but must be filed no more than 6 months after completion of the project. C.R.S. §3249.

If the mechanic lien claimant fails to initiate suit within this 6-month period after completion, the mechanic lien expires and becomes unenforceable. It is critical to monitor the project completion date to ensure timely filing.

Public Works — Payment Bond Suit Deadline (§38-26-101)

On public works projects with contracts over $50,000, suit on the payment bond must be filed within 6 months after substantial completion of the project or 90 days after the date of final settlement, whichever is later. C.R.S. §38-26-101 et seq.

If the payment bond itself provides for a longer period to file suit, the bond's terms control over the statutory deadline. Claimants should carefully review the bond language for any extended filing periods.

Public Works — Claim Against Unexpended Funds (§38-26-107)

For claims against unexpended funds on public projects, the claimant must file a Verified Statement of Amount Due/Mechanic Lien on Funds with the owner or public authority at any time up to final settlement of the project.

Suit must be filed within 90 days after the date of final settlement. A Lis Pendens is required to be served on the government entity when filing suit.

  • File Verified Statement of Amount Due with public authority before final settlement
  • File suit within 90 days after final settlement
  • Lis Pendens must be served on the government entity

No Preliminary Notice Required for Public Works Suits

Colorado does not require any preliminary notice from contractors, subcontractors, materialmen, or laborers before filing suit on a public works payment bond or pursuing a claim against unexpended funds.

However, for unexpended funds claims, the Verified Statement of Amount Due must be filed before final settlement to preserve the claim.

Automatic Mechanic Lien Expiration

A Colorado mechanics' mechanic lien that is not enforced by filing suit within 6 months after completion of the project automatically expires. The claimant loses all mechanic lien rights and must pursue other remedies such as breach of contract or trust fund claims.

The trust fund remedy may provide an alternative path to recovery even after mechanic lien expiration, as all funds disbursed to any contractor or subcontractor are impressed with a trust under Colorado law.

Frequently Asked Questions

How long do I have to enforce a Colorado mechanics' mechanic lien?

Suit may be filed at any time after performance but must be filed no more than 6 months after completion of the project.

When can I sue on a Colorado public works bond?

Suit must be filed within 6 months after substantial completion or 90 days after final settlement, whichever is later. If the bond provides a longer period, the bond controls. This applies to contracts over $50,000 under C.R.S. §38-26-101.

What is the unexpended funds claim in Colorado?

On public projects, claimants can file a Verified Statement of Amount Due/Mechanic Lien on Funds with the public authority before final settlement. Suit must then be filed within 90 days after final settlement with a Lis Pendens served on the government entity. C.R.S. §38-26-107.

Do I need to give notice before suing on a Colorado public bond?

No. No preliminary notice is required before filing suit on a public works payment bond in Colorado.

What happens if I don't enforce my Colorado mechanic lien in time?

The mechanic lien automatically expires after 6 months from project completion. However, you may still have a trust fund claim, as Colorado impresses a trust on all funds disbursed to contractors and subcontractors.

Is a Lis Pendens required in Colorado?

A Lis Pendens is required when filing suit for claims against unexpended funds on public projects. It must be served on the government entity.

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.

Contact Us